1. The beach loungers now have new lettering (Return Me 2 Dune Line) as a result of a good suggestion by board member, Gene Fine. (see above). Seems to be working.
2. Work on the Gate Arms for the Bldg. 3 garage is scheduled to begin this coming Wednesday, July 31.
3. The deck coating project is progressing. The caulking is being done around Bldg 2. The south parking lot still needs to be scraped however, that crew was way ahead of the crews behind. To date, approximately 2,000 linear feet has been caulked north of Bldg 3 and in the front spaces (see above).
4. Concrete work on Bldg. 1 did not pass inspection. The contractor will return today, Monday, to finish up with the railings and start on repairs related to inspection.
(as per Jean Le Grys - Weekly Highlights to board members, week ending 072613)