1. Ongoing projects status:
JES our concrete restoration company has completed 97% of the work in Bldg. #3.
We are ready for walk through and final inspection.
Bldg. 2 concrete work is ongoing with 60% of the work completed.
Work under the south deck parking area is 80% completed.
Four areas around the north pool in the parking garage are 60% completed.
We are on budget and anticipate completion in 3 to 4 weeks.
2. Picture Perfect Pools has removed 4 layers of old diamond bright which was not anticipated,
We have identified 50 square feet of concrete that needs restoring. As of this report that has been
completed and the contractor has started installing tiles. A wider and longer coupling will be installed
to meet new codes. We will also have an auto water feeder, new LED lighting as well as ladders and
hand rails. We anticipate completion by Mid-September.
3. David Branin a member of our maintenance crew has left us to pursue another career. We wish him
future success. He has been replaced by Rubin Lopez. Welcome aboard Rubin!
4. We have replaced the loop under the pavers by the south exit gate. The loop is the device which
signals the arm to go up and down.
5. GCC has repaired 20 spots in the membrane on the deck throughout the property.
6. The toilet in the inside men's room of Bldg. 3 has been replaced.
7. We replaced 8 florescent light ballasts in the parking garage between Bldg. 1 and Bldg. 3