Coming Soon - a Slide Show of Pictures of the AE Roofing Project
1. The Re-roofing project is 100% completed. All building permits have been signed off by the building Dept. Pending final releases and completion of punch list items we will release retainage. (See men at work on April 2 and completed roof, April 22 in pictures above).
2. The new generator has been installed and tested. We are waiting for Building Dept. sign Off.
3 .Re-wiring of the roof fans is 99% completed. A punch list has been developed and John Cramer will be addressing the issues.
4. The New Ambassador signs are in my office. Staff is prepping the metal enclosures, replacing angle iron frame, scraping and painting. (Update: The new signs (entry & exit) have been installed. See below)
5. Tuesday June 3, there will be a special Board Meeting @ 3PM. On the agenda are two items: Signing contract with JES (concrete project) and approval of sealing the pavers on the driveway (strand).
6. Bldg. #2 will be inspected by our engineer for cracks in deck and wing walls.
7. All units have been inspected for tar and rocks, those units that have issues will be addressed Monday, by Infinity Roofing. The management would like to thank the following board members for inspecting every balcony in all 3 buildings and preparing a punch list of affected units: Ruth Halle, Nikki Lischinsky, Valle Ingram, Alice Keller and John Bird.
8. Mitigation reports are completed for Bldg. 1, 2 and 3 roofs and deck. Reports have been forwarded to Andrea at our insurance agency.
(Report as per Manager Basil Aiello - Excerpts from his Weekly Update to board members, week ending 05/30/14)